CA-7 scheduling help

Posted: Mon Aug 07, 2017 4:48 pm
by MikeL
Don't know if this can be done in CA-7, anyone have a suggestion?

We have a job that kicks off based and the presence of a dataset. The job in turn kicks of the OnDemand product to import the contents of the dataset. The problem is that the dataset has started being created during the downtime of OnDemand, causing the job to crash. Is there a way to say:

"Kick it off when the dataset is created, but not during the hours of midngiht-1:30am"